Roof Top Equipment Platform Structure.

  • Timeframe: 15 days
  • Tonnage: 74
  • Project location: USA

Synopsis

Ferramatrix and its team was involved in developing the design for a rooftop equipment platform that supported various telecommunication antennas in the city. These platforms were designed for Verizon and its antenna installations. The platform was galvanized and it supports small communication equipments along with antennas with the shop drawings delivered within 15 days.

The structure also offered a rational response to a series of programmatic requirements with a functional, contemporary, and contextual platform that delivers space for telecommunication antennas in a structured manner with adequate steel members set along a rectangle.

Takeaways

The rationalized geometry approach conveyed the plan in three-dimensional plans and elevations through Tekla imagery, allowing standard steel fabricators to implement it efficiently.